Germany’s data centre industry will invest a record 23.5 billion euros this year, 57 per cent more than in 2025, and yet the new Bitkom market study expects the country to miss its own 2030 capacity target by around 500 megawatts. Only one euro in four goes into buildings and building technology; the rest buys servers. For investors in land and shells, the study is a map of where the gap between money and megawatts opens up, and why.
A record year that still falls short
The study “Rechenzentren in Deutschland 2026”, prepared for the digital association Bitkom by the Borderstep Institute and presented on 3 November, puts investment in German data centres at 23.5 billion euros for 2026, after 15 billion euros in 2025 and 12.9 billion euros in 2024. Installed IT connection capacity rises to 3,300 MW this year, 300 MW more than in 2025. Since 2015, when Germany had 1,660 MW, capacity has almost doubled.
The political benchmark is the federal government’s data centre strategy of 18 March 2026, which aims to at least double capacity by 2030 and to at least quadruple AI and high performance computing capacity. Bitkom translates the doubling into an approximate target of 6,000 MW. Its own trend forecast for 2030 is 5,500 MW, a shortfall of about 500 MW or eight per cent. Borderstep, which presented the figures again at the Bitkom Data Centre Summit on 12 November, puts it plainly: despite strong growth, the political targets will probably not be fully reached.
The arithmetic matters. Capacity grew by about 250 MW in 2025 and by 300 MW in 2026. Reaching 5,500 MW by 2030 requires 2,200 MW in four years, or 550 MW a year, roughly double the current pace. The 6,000 MW target requires 675 MW a year. Even the forecast that misses the target assumes a build rate Germany has never achieved.
Where the euros go: hardware, not halls
For property investors the most useful number in the study is the split of the 23.5 billion euros. Around 18 billion euros, or 77 per cent, buys IT hardware such as servers and storage, up from 12 billion euros in 2025. Buildings and building technology account for about 5.5 billion euros, up from 3 billion euros in 2025 and 2.9 billion euros in 2024. The real estate component is therefore growing faster than the total, by 83 per cent in a year, but it remains below a quarter of the headline figure.
This is the structural reason why capacity grows more slowly than investment. AI accelerators are expensive and dense: Bitkom puts AI and HPC at 20 per cent of capacity in 2026, 670 MW, rising to around 36 per cent, more than 2,100 MW, in 2030 and 55 per cent, 5,300 MW, in 2035. A growing share of each new euro is spent on what sits in the rack rather than on the hall around it. The 5.5 billion euros for buildings and building technology is, in effect, the size of the addressable market for developers, landlords and construction lenders this year. In August we asked who is financing Germany’s data centre boom; the Bitkom figures show the building side of that question nearly doubling in twelve months.
The pipeline is not the problem, delivery is
The regional figures show that the gap to 2030 is not a shortage of projects. Hessen, with around 1,200 MW installed, has 2,000 MW under construction. Brandenburg, with roughly 104 MW in operation, has 1,301 MW under construction, a twelvefold increase that we analysed in our article on the eastward shift of the German pipeline. North Rhine-Westphalia adds 450 MW. The three states alone report 3,751 MW in construction, more than the 2,200 MW that the trend forecast adds by 2030 and more than the 2,700 MW the political target would require.
What stands between construction sites and connected megawatts is the grid, followed by permits. In the Borderstep survey reported by dpa, around 80 per cent of operators and experts named limited grid connection capacity as the biggest obstacle; Bitkom calls grid capacity and slow permitting a massive bottleneck. In Frankfurt, according to JLL’s mid-year report, vacancy stood at 3.1 per cent in the second quarter, with 311 MW in development and 687 MW planned, but connection lead times of 24 months or more pace delivery.
The legislative answer is in the Bundestag. The grid connection package, a government bill to replace the first come, first served principle with uniform rules for prioritisation, reservation and transparency, also allows grid operators to reduce connection capacity that has not been fully used. The Bundesrat asked on 25 September for a three year look-back instead of the five years in the government draft, with ramp-up, expansion, redundancy and security needs to be considered before any cut; the German Datacenter Association warns that three years do not reflect a data centre’s ramp-up. The digital ministry reported in September that 25 of the strategy’s 28 measures had started, four were completed and five were in parliament. Only 20 per cent of the operators surveyed by Bitkom expect rapid implementation, and just 33 per cent consider the targets ambitious enough.
Demand is not waiting for the grid
While Germany debates its 500 MW, the European market is tightening. CBRE reports that vacancy in the five core markets of Frankfurt, London, Amsterdam, Paris and Dublin fell to an all-time low of 5.8 per cent in the third quarter of 2026, 2.2 percentage points lower than in the second, and expects colocation take-up of 1.34 GW to exceed new supply of 1.26 GW this year, the first time in the region. JLL puts prime powered land in the core markets at 2.26 million euros per megawatt, 82 per cent more than in 2021, with primary markets commanding a 2.3 times premium over secondary locations and four times over tertiary ones.
Germany remains Europe’s largest market, with 3.3 GW against 2.9 GW in the United Kingdom, 2.0 GW in France and 1.7 GW in Ireland, and Bitkom expects it to keep the lead at 5.5 GW in 2030 against 4.0 GW for the UK. The comparison that worries Bitkom is a different one: the United States had around 47 GW in 2025 and China 22 GW, and the study expects 160 GW and 90 GW respectively by 2035, against 37 GW for all of Europe. Electricity demand follows the capacity: around 23 billion kilowatt hours in Germany this year, rising to 35 to 38 billion in 2030, even though the average PUE has fallen from 1.63 in 2020 to 1.42.
What this means for investors
- The constraint has a price, and it is rising. With European core market vacancy at a record low and powered land at 2.26 million euros per MW, a German site with a signed grid connection is scarcer than the 23.5 billion euro headline suggests. Value sits in the connection and the permit, not in the hall.
- Size the real estate opportunity at 5.5 billion euros, not 23.5 billion. Three quarters of this year’s investment buys hardware. Developers and lenders should model building and building technology capex, which is growing at over 80 per cent a year, as their market, and expect hyperscalers and AI tenants to carry the equipment.
- Pipeline figures are not delivery figures. 3,751 MW under construction in three states will not all be energised by 2030. In due diligence, separate projects with a binding connection and a construction permit from those with a reservation and a plan; the forecast gap of 500 MW is made of the second group.
- Model the grid connection package. A reduction of unused capacity after three or five years changes how phased campuses are structured. Reservation contracts, ramp-up schedules and redundancy should be documented to match the criteria the Bundestag finally adopts.
- Diversify beyond Frankfurt with care. Brandenburg’s 1,301 MW and Hessen’s 2,000 MW under construction will compete for the same transformers and permitting staff. A secondary location with an existing substation and a utility partner can deliver earlier than a Frankfurt plot with a 24 month queue.
This is the terrain on which Prime East works through its dedicated division PE Property Solutions: site and grid connection assessment, technical due diligence, structuring of operator and lease models, and transaction support for data centre projects in Germany and Poland.
Conclusion
The Bitkom study describes a market that has never invested more and still cannot build fast enough. Germany adds 300 MW a year and needs 550 to 675 MW a year to meet its own forecast or its own target. The money is there, but three quarters of it goes into servers, and the megawatts that would close the gap are waiting on substations, permits and a law the Bundestag is still debating. For investors this is not a reason to stay away. It is a reason to buy the scarce thing, which in Germany in 2026 is a connected, permitted site, and to treat every pipeline number as a question rather than an answer.
Talk to us
Do you own land with grid capacity in Germany or Poland, or are you evaluating a data centre project whose connection and permit timeline decides its value? Prime East assesses sites, connection options and operator structures, and brings investors, landowners, utilities and operators together. Contact our team for a confidential discussion of your investment or project enquiry.
Disclaimer: This article is for general information only and does not constitute investment, legal or tax advice. All figures are based on publicly available sources.
Sources
- Bitkom: KI-Boom treibt Rechenzentren in Deutschland – dennoch bauen USA und China Vorsprung aus (3 November 2026)
- Borderstep Institut: 23,5 Mrd. €: Investitionen in deutsche Rechenzentren auf Rekordniveau (16 November 2026)
- Handelsblatt/dpa: Digitalgipfel: KI-Boom lässt Strombedarf von Rechenzentren stark steigen (3 November 2026)
- ComputerBase: Rechenzentren: Rekordinvestitionen in Deutschland, aber USA und China enteilen (3 November 2026)
- Bundesministerium für Digitales und Staatsmodernisierung: Halbjahresbilanz Rechenzentrumsstrategie (18 September 2026)
- ZfK: Bundesregierung beschließt Rechenzentrumsstrategie (18 March 2026)
- German Datacenter Association: GDA positioniert sich zum Netzanschlusspaket (22 July 2026)
- Deutscher Bundestag: Drucksache 21/8299, Stellungnahme des Bundesrates zum Netzanschlusspaket (30 September 2026)
- JLL: EMEA data centre mid-year 2026 report (3 August 2026)
- CBRE: European Data Centres Figures Q3 2026 (16 November 2026)